We have completed our color selections and chosen all upgrades and additions to the home. Here is the list of standard features for our subdivision. Here is the list of upgrades we have made

We have determined the position and orientation of the home on the lot, here is the  lot fit plan

As part of our color selections we have also chosen the brick color. It will be Arkansas Rose manufactured by ACME Brick. Here is an example of a house with this brick.

See the current errors page for currently outstanding items for the builder to resolve.  Also see the Detailed errors page for detailed descriptions of all the things that went wrong during the construction process.

For future reference I took pictures of each wall & ceiling in the house before sheetrock was hung so that I would know what is behind the walls.

First Floor Walls
Second Floor Walls

 

Use the links below to access monthly pages containing detailed notes with pictures.

June Clearing the lot & preparing for the foundation
July Pour foundation and begin framing
August Finish framing, HVAC, Electrical, Plumbing, Roof,
September Sheetrock, Brick, Cabinets, Trim
October Fence, Electrical, Plumbing, Paint
November Construction Complete 11/11/2003

 

Detailed Errors Main House Punch List