The end of June saw construction actually begin on the home. Many trees were
removed to make room for the slab plus 5 foot around the slab. The forms were
also starting to be set.
Week of 6/16
Initial clearing of the lot for the foundation
Just as a reminder, here is the lot before it was cleared
West Side
West Side 2
West Side 3
Center
East Side
After the lot was cleared
West Side
West Side 2
West Side 3
West Side 4
East Side
East Side 2
East Side 3
Week of 6/23
Prepare ground for foundation and lay forms for foundation.
We also had our first meeting with the General Contractor, Jeff
Lot, West Side
Lot, East Side
Forms, Front of house
Forms, Garages
Forms, Garages 2
Forms, Patio
Forms, Master Bedroom
Week of 6/30
Prepare inside of forms for foundation. Cut curb for driveway